The location of the city of Belgrade, lying at the intersection of three important transport corridors (IWW Corridor Rhine-Danube as well as road and railway Corridor X), provides the possibility of projecting competitive transshipment results. The new Port of Belgrade has the potential to become one of the major transportation and distribution nodes in a broader geographic area including Belgrade, Central and South Serbia, east and southeast Srem and Banat. The construction of the railway line connecting the Port of Piraeus with Central and North Europe will provide access to additional multimodal logistic services to the proposed Port of Belgrade along its route enabling the connection of inland waterways with railway and road corridors. The Project is of strategic relevance and it was included in the Single Project Pipeline. This Project ranks as the fifth most important transport sector project.
The general objective of the Project is to provide a multimodal transport hub that will enable the connection between the future New Port of Belgrade and inland waterway TEN-T Rhine-Danube Corridor with the axes of the most important Serbian roads (E-70, E-75, regional road Belgrade-Vrsac and Belgrade-Zrenjanin), as well as with the railway Belgrade-Kelebija (Budapest). The Project Railway Corridor X Rehabilitation in Serbia with its Xb and Xc branches, as well as the construction of the railway connection between the New Port of Belgrade and the Belgrade-Kelebija railway line, will provide connection of the New Port of Belgrade to some of the most important TEN-T corridors, such as the Orient/East-Med Corridor, the Mediterranean Corridor and the Baltic-Adriatic Corridor.
WBIF | Grant | WB20-SRB-TRA-02 | € 804,000 |
EBRD | Loan | € 19,900,000 | |
EIB | Loan | € 52,230,000 | |
National Contribution | Own Contribution | € 16,020,000 | |
Anticipated WBIF TA Grant | External Grant | € 2,250,000 | |
Anticipated WBIF TA Grant | External Grant | € 3,770,000 | |
Anticipated WBIF INV Grant | External Grant | € 14,850,000 | |
Total | € 109,824,000 | ||
Total Grants | € 804,000 | ||
Total Loans | € 72,130,000 |